I posted an update to redcrests post Marinaut 215 any updates? but wanted a new thread started about it so this post.
It is really going to happen. I can see light at the end of the tunnel.
I have updated our web site and added the following
24th of March 2010
It has been a long three year process to design and do the tooling for the Marinaut 215 and now all the tooling has been completed.
The design was changed from the original 205 to the 215 and then some minor changes after the initial 215 design as we did the tooling. Those design changes were done to facilitate the assembly process with one exception which is a slightly raised center line of the cabin roof. This was done to give the 6' 4" person head room in the cabin.
There are nine separate molds for the various parts of the Marinaut and they range from fairly simple ones to detailed and substantial ones. The parts for the first boat has been produced and the first Marinaut 215 is going together and should be completed next week with one exception. Our window supplier has told us the first window pack will not be ready until the 12th of April so the completion date for the first boat will be sometime in the second half of April.
Preliminary calculations of our fuel tanks indicate they will be just under 30 gallons each instead of our original 25 gallon estimates. This will be updated when we fill it for the first time.
Our official launch date will be the end of April or the first week in May at Swantown in Olympia, WA. The public is invited and a firm date will be decided early in April. We also plan to have the Marinaut 215 at the C-Brat gathering in Friday Harbor the 14th, 15th and 16th of May 2010.
Photos of the history/build process are Here
I pick up the fuel tanks tomorrow morning at Coastline Equipment in Bellingham, WA.
_______
Dave
www.tolandmarine.com
It is really going to happen. I can see light at the end of the tunnel.
I have updated our web site and added the following
24th of March 2010
It has been a long three year process to design and do the tooling for the Marinaut 215 and now all the tooling has been completed.
The design was changed from the original 205 to the 215 and then some minor changes after the initial 215 design as we did the tooling. Those design changes were done to facilitate the assembly process with one exception which is a slightly raised center line of the cabin roof. This was done to give the 6' 4" person head room in the cabin.
There are nine separate molds for the various parts of the Marinaut and they range from fairly simple ones to detailed and substantial ones. The parts for the first boat has been produced and the first Marinaut 215 is going together and should be completed next week with one exception. Our window supplier has told us the first window pack will not be ready until the 12th of April so the completion date for the first boat will be sometime in the second half of April.
Preliminary calculations of our fuel tanks indicate they will be just under 30 gallons each instead of our original 25 gallon estimates. This will be updated when we fill it for the first time.
Our official launch date will be the end of April or the first week in May at Swantown in Olympia, WA. The public is invited and a firm date will be decided early in April. We also plan to have the Marinaut 215 at the C-Brat gathering in Friday Harbor the 14th, 15th and 16th of May 2010.
Photos of the history/build process are Here
I pick up the fuel tanks tomorrow morning at Coastline Equipment in Bellingham, WA.
_______
Dave

www.tolandmarine.com